Timeline

Key project milestones and their dates are shown below by year of occurrence:

2018
January

Construction commences

2017
November

Financial Close achieved

2017
September

Transmission Connection Agreement and EPC Contract signed

2017
May

LGC contracts with ERM Power signed

2017

Development approval extended and wind turbine heights changed to 180m

2015

Nexif took over management in November

2014

Development approval extended and wind turbine heights changed to 150m, with a new 59 wind turbine layout

2013

Project sold to OneWind Australia Pty Ltd

2009

Two wind measurement masts installed

2006

Development approval granted

2004

Site identified by Wind Energy Solutions and development begins