Key project milestones and their dates are shown below by year of occurrence:
2021
December
Stage 2 first generation into grid
2020
August
Stage 2 construction commences
2020
May
Stage 1 achieves commercial operation
2019
April
First generation and energy export to the grid
2018
January
Construction commences
2017
November
Financial Close achieved
2017
September
Transmission Connection Agreement and EPC Contract signed
2017
May
LGC contracts with ERM Power signed
2017
Development approval extended and wind turbine heights changed to 180m
2015
Nexif took over management in November
2014
Development approval extended and wind turbine heights changed to 150m, with a new 59 wind turbine layout
2013
Project sold to OneWind Australia Pty Ltd
2009
Two wind measurement masts installed
2006
Development approval granted
2004
Site identified by Wind Energy Solutions and development begins